<br />Week 4 <br /> <br />I. Set new 250kw generator in place and anchor. <br />2. Set new service distribution rack. <br />3. Set new 1200 amp Automatic Transfer Switch (ATS) in place. <br />4. Scnedule for load test and sign off with generator manufacture for new 250kw <br />generator. <br /> <br />WeekS <br /> <br />1. Wire new power feed from Power Company transformer to 1200 amp ATS. <br />2. Wire new power feed from 1200 amp ATS to MDP in main electrical room. <br />3. Wire new power feed from 1200 amp ATS to new 250kw generator. <br />4. Wire new power feed from new circuit breaker in MDP. <br />5. Schedule power outage for following week for connection of new power feed in <br />MDP. <br /> <br />Week 6 <br /> <br />1. Terminate wire on 1200 amp ATS, 250kw generator, and MDP. <br />2. New 1200 amp service completed into building. <br />3. Existing 125kw generator disabled. <br />4. Locate underground utilities at Public Works Building. <br /> <br />Week 7 <br /> <br />1. Remove existing privacy fence around existing Public Works Building 75kw <br />generator. <br />2. Existing 75kw generator disabled. <br />3. Remove existing 75kw generator and service distribution equipment. <br /> <br />WeekS <br /> <br />1. Run underground conduits for the Public Works Building relocated 12Skw <br />generator. <br />a. Directional bore across parking lot from new Power Company transformer <br />to new service distribution rack. <br />b. Run underground conduit from new service distribution rack to MDP in <br />main electrical room. <br />c. Run underground conduit ITom new service distribution rack to relocated <br />125kw generator.. <br />3. Back fill open trenches. <br />4. Patch concrete cut across sidewalk. <br />