Laserfiche WebLink
<br />CDM <br /> <br />Scope of Work <br /> <br />Subtask 1.3 - Cafe Area Re-Design <br />The ENGINEER will re-design the cafe area so that it is shifted to the northeast corner <br />of City Hall. This will include sidewalk modifications, landscape screening for the <br />chiller, and inclusion of additional landscape species. <br /> <br />Subtask 1.4 - Shower Installation Design <br />The ENGINEER will coordinate with the CITY's preferred vendor to design for the <br />installation of a shower (required by state law for the interactive fountain). The <br />ENGINEER will design for the associated piping near the cafe area described in <br />Subtask 1.3. <br /> <br />Task 2 - Civil Design <br /> <br />Subtask 2.1 - Stormwater Pond Reuse COllnections <br />The ENGINEER will design the connections between the irrigation line coming from <br />the stormwater pond on Triplet Lake Drive and the existing 4-inch reclaim main. The <br />design will show necessary appurtenances (Le., backflow preventers) as well as <br />existing reclaimed water mains. <br /> <br />Task 3 - Electrical <br />Subtask 3.1 - Landscape Lighting <br />The ENGINEER will provide design for landscape lighting throughout the park. This <br />will be separate from the acorn lights to be placed by Progress Energy. Path lighting <br />(separate from Progress Energy) will be provided on the sidewalk connection to the <br />Art House (HHI) and the boardwalk (CDM). The ENGINEER will use Tahoe 501 <br />(Circular Outward Light Pattern Tahoe Bollards), 24-inch as recommended by the <br />CITY for path and area lighting. The CITY will provide AutoCAD files from Progress <br />Energy for acorn light locations that the ENGINEER will incorporate into the design <br />drawings. <br /> <br />Subtask 3.2 - Wiring for Stage and Soulld System <br />The ENGINEER will design pull boxes, conduit and wiring for power to the stage <br />based on electrical loading information provided by the CITY's electrical contractor <br />(Le., Teer Engineering). The ENGINEER will also design pull boxes and conduit to <br />speaker locations as per the CITY's electrical contractor's recommendations. <br /> <br />Subtask 3.3 - Photometric Plan/Boardwalk Lighting <br />The ENGINEER will prepare a photometric plan for the park that is consistent with <br />the CITY's Code of Ordinances. Preparation of such a plan will also satisfy the SI. <br />Johns River Water Management District's (SJRWMD) comment in the Request for <br />Additional Information (RAI) dated July 15, 2008. Additionally, the ENGINEER will <br />incorporate timers into the lighting design for the boardwalk. <br /> <br />Subtask 3.4 - Relocation of Aeration & Fountain Equipment <br />The ENGINEER will relocate the aeration equipment currently located at the <br />northeast corner of the existing detention pond to the north end of the Art House. <br />The relocation of this equipment will be noted on both the demolition plan and the <br />electrical plans. In the 90 percent design drawings, the ENGINEER had previously <br /> <br />S:\OOOO\8WMNB\CasselberrvlScope a~d BudgoelISOOPf,! _ 08Sep08doc~ <br /> <br />2 <br />