<br /> <br />Wirz Park Trail (Section 2) <br /> <br /> <br />· Funding <br />- Seminole <br />County <br />($1 million) <br />· Challenges <br />- School <br />schedule <br />-Utility <br />relocations <br /> <br /> <br />BEFORE <br /> <br />AFTER <br /> <br /> <br />· Combination of asphalt and concrete <br /> <br /> <br />Wirz Park Trail (Section 2) <br /> <br />. Timeline <br />- Construction <br />contract <br />expected: <br />May 11, 2009 <br />- Anticipated <br />construction <br />start: June <br />2009 <br />Anticipated <br />construction <br />completion: <br />end of 1't <br />quarter 2010 <br /> <br /> <br /> <br />Trailhead to Zinnia Trail <br /> <br />· Use of boardwalk to traverse through <br />wetlands <br /> <br /> <br /> <br />Casselberry <br />Elementary to <br />Crystal Bowl Park <br /> <br />· Combination of <br />asphalt and concrete <br /> <br />2 <br />